employer cover photo
employer logo
employer logo

Defence Construction Canada/Construction de Défense Canada

Engaged Employer

Defence Construction Canada/Construction de Défense Canada Interview Question

Describe the change order process.

Interview Answer

Anonymous

Feb 11, 2019

When contract documents don't provide enough or the correct information, the contractor will send an RFI to the consultant. If there needs to be a change to the design, it is issued in a CCN. Once the work is priced, the contractor will submit a quote to the owner/consultant, if approved, a change order is issued and the work proceeds as per the CCN.

5